A project takes 4 workers 6 hours to complete. How long would it take 3 workers to complete the same project?
Answer
8 hours

๐Ÿ“ Step-by-Step Solution

1
Total work: 4 workers ร— 6 hours = 24 worker-hours
2
Workers available: 3
3
Time needed: 24 รท 3 = 8 hours
๐Ÿ’ก Helpful Hints
โ€ข Calculate total work needed
โ€ข How many workers are available?
โ€ข Divide total work by number of workers